Below is the State Corporation Commission Schedule for the proposed upgrades between Possum Point and Smoketown substations in Woodbridge, VA. Work s proposed to be within existing rights of way. An Order for Notice and Hearing was issued this week for the Possum Point-Smoketown Rebuild Project.  The procedural schedule follows:

07/28/17 – Landowner and Government Official Notice
08/11/17 – Newspaper Notice
08/25/17 – Proof of Notice and Certificate of Mailing
08/25/17 – Notices of Participation
09/08/17 – Respondent Testimony
09/14/17 – Public Hearing, Fitzgerald Elementary School, Woodbridge, 7:00 pm
09/28/17 – Staff Report due
10/12/17 – DVP Rebuttal due
10/26/17 – Public Comments
11/02/17 – Public Evidentiary Hearing, 10:00 a.m., SCC

Find more project updates on the Dominion website.

Leave a Comment

Things move quickly in New Woodbridge! Get updates from the Office of Supervisor Frank Principi for the latest in...
  • Community News
  • Events & Activities
  • Opportunities to Make a Difference

Just enter your email below to stay in the know!

By submitting this form, you are granting: Woodbridge Supervisor Frank J. Principi, 15941 Donald Curtis Drive, Woodbridge, VA, 22191, permission to email you. You may unsubscribe via the link found at the bottom of every email. (See our Email Privacy Policy (http://constantcontact.com/legal/privacy-statement) for details.) Emails are serviced by Constant Contact.


By submitting this form, you are granting: Woodbridge Supervisor Frank J. Principi, 15941 Donald Curtis Drive, Woodbridge, VA, 22191, permission to email you. You may unsubscribe via the link found at the bottom of every email. (See our Email Privacy Policy (http://constantcontact.com/legal/privacy-statement) for details.) Emails are serviced by Constant Contact.

Subscribe!